orange cones, construction

Photo courtesy of Metro

Earlier this month, Lake Highlands Advocate reported on construction at the intersection of Audelia Road and Northwest Highway, where Dallas Water Utilities (DWU) is installing a new valve designed to improve the reliability of the city’s drinking water system.

Since the initial report, DWU has provided additional details about why the intersection was selected for the improvements, how the new valve will benefit North and East Dallas residents and what to expect once construction is complete.

DWU also shared information about a separate storm drainage improvement project underway near Guildhall Road and McCree Road in northeast Dallas.

Why the Audelia Road intersection? 

According to DWU, its drinking water system is divided into several pressure zones that are isolated from each other. Two of the largest pressure zones in the DWU system are the North High and East High, which share a border along Northwest Highway. 

DWU said an engineering analysis recommended adding the new valve to allow for interconnection of the two pressure zones when needed. This would improve system resiliency and pressure delivery. 

The intersection of Audelia Road and Northwest Highway was chosen because of proximity to existing water mains serving the pressure zones. . 

What residents can expect

The North High and East High pressure zones include most of North and East Dallas and account for more than 25% of DWU’s daily water demand. Improving reliability in those zones will benefit tens of thousands of homes and businesses, according to DWU.

Under normal conditions, the two pressure zones operate independently. However, during an emergency affecting one zone, the new valve can be remotely opened to allow a controlled volume of water to flow form the neighboring zone, helping maintain adequate water pressure in both areas.

DWU said residents should not notice any difference in water pressure or system performance once construction is complete. The work is being completed without shutting down the water distribution mains serving nearby neighborhoods. Residents should not experience disruptions to their water service during construction.

Executive Drive water tank project

The new elevated storage tank (EST) on Executive Drive will replace an EST near Garland Road.

DWU said the tank replacement is not directly related to the new valve at Audelia Road and Northwest Highway. However, the two projects were combined because of their timing and geographic proximity. 

Guildhall-McCree Storm Drainage Relief System Project

DWU began construction work on its Guildhall-McCree Storm Drainage Relief System Project in July. The project aims to address recurring flooding near Guildhall Drive and McCree Road.

The existing storm sewer system is undersized and unable to adequately convey runoff during a 100-year storm, contributing to structural, yard and street flooding, according to DWU. 

The project extends along Aldwick Drive from McCree Road to Shoreview Road, with additional work along Audelia Road, Linkwood Drive and Ferndale Road. 

Construction will include removing and replacing existing storm drainage pipes and increasing the capacity of the drainage system. The work includes approximately 7,034 linear feet of storm drainage infrastructure and 11,152 feet of water and wastewater improvements.

The contractor, SYB Construction Company Inc., has completed storm drainage pipe installation along Shoreview Road and Aldwick Drive to Lanshire Drive and has begun wastewater line installation in the same area. 

The project is expected to be completed in Summer 2027.